Install Window A/C Units in Rolling Pin Barracks
Fort Leonard Wood, Missouri
Brief scope of work: Install window air conditioners in barracks. Also includes updating of electrical distribution system and service entrance. Total of 18 buildings included in contract.
|
Contract Information |
||
|
Contract Owner |
ACA Ft. Leonard Wood, Directorate of Contracting |
|
|
Contract Number |
W911S7-04-C-0010 |
|
|
Contract Type |
Sealed Bid |
|
|
Contract Value |
$1,728,000.00 |
|
|
Period of Performance |
March 2004 – August 2005 |
|
|
Contracting Officer |
Julie Meyer |
(573) 596-0260 |
|
Contract Administrator |
Donna Hickey |
(573) 596-0254 |
|
Technical Representative |
Pat Brugger |
(573) 596-0907 |
|
Technical Representative |
Tom Magruder |
(573) 596-0914 |



Replace Fascia on Buildings in 1700 Area
Fort Leonard Wood, Missouri
Brief scope of work: Remove old and install new fascia on 46 Buildings in 1700 Area of Fort Leonard Wood, Missouri.
|
Contract Information |
||
|
Contract Owner |
ACA Ft. Leonard Wood, Directorate of Contracting |
|
|
Contract Number |
DABT31-02-C-0012 |
|
|
Contract Type |
Sealed Bid |
|
|
Contract Value |
$1,132,216.99 |
|
|
Period of Performance |
May 2003 - April 2004 |
|
|
Contracting Officer |
Carroll Saddler |
(573) 596-0610 |
|
Contract Administrator |
Marilyn Bassett |
(573) 596-0250 |
|
Technical Representative |
Jim Brant |
(573) 596-0907 |


Restation ADA School, Center Level Renovations, Building 700
Fort Sill, Oklahoma
Brief scope of work: Installation of civil architectural finishes including flooring, painting, acoustical ceilings, doors, frames and hardware. Also includes masonry infill, toilet partitions and bath accessories.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
W912BV-07-R-2038, COE001-006 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$1,350,342.85 |
|
|
Period of Performance |
February 2008 - July 2009 |
|
|
Contracting Officer |
Tom Medina |
(270) 442-8620 |

Renovate Building 34, Phase I Part I
Naval Support Activity, Crane, Indiana
Brief scope of work: Provide all labor, equipment, tools, supplies, transportation, supervision, quality control and management necessary to design and construct new work areas in Building 34 including demolition and reconstruction of GWB and CMU walls, installation of new stairwell, mezzanine, new storefront, interior and exterior, soundproof and roll-up doors & hardware, new ceiling tile and grid, upgraded fire suppression system, new static dissipative tile flooring, carpeting, painting, relocating AHUs and associated controls, piping and ductwork, installation of electrical systems components, painting, site work including installation of a new sprinkler water line, new potable water service line, backflow preventer and hydrant.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest PWD Detachment, Crane |
|
|
Contract Number |
N40083-09-C-2218 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$771,764.00 |
|
|
Period of Performance |
January 2009 – August 2009 |
|
|
Contracting Officer |
Tim Curry |
(812) 854-3537 |
BEFORE AFTER

Building 420 Interior Repair, Phase II
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Demo of drywall, walls, ceilings, flooring and door infill to allow for overhead door replacement, new drywall, carpeting, VCT, acoustical ceiling tile and grid, and installation of new toilet partitions and bath accessories.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0-006 FRR080-121 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$671,325.00 |
|
|
Period of Performance |
June 2007 – May 2008 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |
BEFORE AFTER

Daycare Facility Demolition, Building 358
NASA Michoud Assembly Facility, New Orleans, Indiana
Brief scope of work: Demolition of interior Building 358 to include ceiling, interior and exterior walls, flooring, fixtures, and playground area. Phase II includes complete rebuilding of interior of Building 358 and re-studding and coverage of exterior walls.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors, Inc., Paducah, KY |
|
|
Contract Number |
FRR080-87 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$509,721.00 |
|
|
Period of Performance |
October 2006 – December 2007 |
|
|
Contract Manager |
Tom Medina |
(270) 442-8620 |
DEMO STAGE

REBUILD COMPLETE
Construct Canteen
VA Hospital, Marion, Indiana
Brief scope of work: Constructed canteen at the VA Hospital in Marion, Indiana.
|
Contract Information |
||
|
Contract Owner |
Veterans Affairs Administration, Marion, IN |
|
|
Contract Number |
IFB610-08-03 |
|
|
Contract Type |
Sealed Bid |
|
|
Contract Value |
$478,000.00 |
|
|
Period of Performance |
July 2003 – March 2004 |
|
|
Contracting Officer |
Marcia Guenin |
(765) 677-3177 |
|
Contract Administrator |
Marcia Guenin |
(765) 677-3177 |
|
Technical Representative |
Sam Elkins |
(765) 674-3321 / 3985 |
Automatic Sprinklers & Fire Alarm System Upgrade
Naval Reserve Center, Louisville, Kentucky
Brief scope of work: Install a wet-pipe sprinkler system, including the installation of a new supply lead-in for the 34,000 square foot main facility of the Naval Reserve Center, Louisville, Kentucky. The project shall include removal of the existing fire alarm system and the installation of a new addressable fire alarm system with an emergency voice evacuation system for the main facility.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-06-C-4586 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$389,673.00 |
|
|
Period of Performance |
August 2006 – December 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |

Fire Protection Systems, Buildings 102 & 160
Naval Support Activity, Crane, Indiana
Brief scope of work: Install wet-pipe automatic sprinkler and fire alarm/mass notification systems in Building 160. Includes the installation of the fire alarm/mass notification for Buildings 3110, 3111 and 3167. Modifications of the Ultra High Speed Deluge Control System to include additional safety equipment at Building 102.
|
Contract Information |
||
|
Contract Owner |
NAVFAC, Midwest PWD Crane |
|
|
Contract Number |
N40083-08-C-2151 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$364,765.00 |
|
|
Period of Performance |
September 2008 – December 2009 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |

Minefill B Compressors, Buildings 3396 & 3397
Naval Support Activity, Crane, Indiana
Brief scope of work: Provide all labor, equipment, tools, supplies, transportation, supervision, quality control and management necessary to construct two facilities and the installation of two complete and ready to use air systems in the Minefill B (MFB) area. Work includes construction of two 18x20 block buildings (new Building 3397 at Building 174 and new Building 3396 at Building 155), electrical systems, site work, air systems, and incidental related work.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest PWD Detachment, Crane IN |
|
|
Contract Number |
N40083-09-C-2217 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$349,135.00 |
|
|
Period of Performance |
January 2009 – October 2009 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |

Building 350 Phase II
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Removal and replacement of ceiling, fencing, window sill replacement, screens, painting, carpeting, bird anti-roosting wires, and canopy curtains.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0-006 FRR080-173 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$331,452.00 |
|
|
Period of Performance |
April 2008 – July 2008 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |
Building 404 Phase II
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Interior renovations of Building 404 including demolition, metal framing and siding, mechanical contracting, drywall installation and finishing, and personnel and overhead door installation.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0-006 FRR080-159 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$277,572.00 |
|
|
Period of Performance |
October 2007 – August 2008 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |
Tower 3291 Window and Insulation Installation
Naval Support Activity, Crane, Indiana
Brief scope of work: This project consists of removing the existing curtain wall system and replacing it with new, and installing External Insulation and Finish System on a 100 foot tower. This project requires an engineered scaffolding system and extensive safety planning.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-05-C-4429 |
|
|
Contract Type |
Negotiated Bid |
|
|
Contract Value |
$277,028.00 |
|
|
Period of Performance |
July 2005 – September 2005 |
|
|
Contracting Officer |
Tim Curry |
(812) 854-3537 |
|
Contract Administrator |
Jeff Franz |
(812) 854-3318 |
|
Technical Representative |
Tim Sears |
(812) 854-3268 |

Renovation of Building 320A
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Provide labor, materials, supplies, equipment, and supervision to prep and paint exterior to include louvers. Also install two doors, frames and hardware per scope of work. Phase II includes rebuild of this building.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors, Inc., Paducah, KY |
|
|
Contract Number |
FRR080-02 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$274,720.00 |
|
|
Period of Performance |
August 2006 – October 2007 |
|
|
Contract Manager |
Tom Medina |
(270) 442-8620 |


Building 126 – High Speed Deluge System
Naval Support Activity, Crane, Indiana
Brief scope of work: Provide labor, transportation, materials, supplies, equipment and supervision to design and install high-speed deluge in the Mix Wing of Building 126 in accordance with contract specifications, complete and ready for use.
|
Contract Information |
||
|
Contract Owner |
NAVFAC, Crane, IN |
|
|
Contract Number |
N40083-06-C-4562 |
|
|
Contract Type |
Lump sum – Design Build, Firm Fixed Price Basis |
|
|
Contract Value |
$267,845.00 |
|
|
Period of Performance |
June 2006 – July 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) -854-6641 |
Modify Secure Area, Building 2
Naval Support Activity, Crane, Indiana
Brief scope of work: Provide all labor, equipment, tools, supplies, transportation, supervision, quality control and management necessary to divide current work area into two by adding a secure entry into Work Area 2 with support space. Work will include demolition and rebuild of walls, relocation of AHU, new intrusion detection system (IDS) and construction of secure entry access.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest PWD Detachment, Crane IN |
|
|
Contract Number |
N40083-09-C-2222 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$258,083.00 |
|
|
Period of Performance |
March 2009 – November 2009 |
|
|
Contracting Officer |
Annette Taylor |
(812) 854-2673 |
Replace Elevator, “W” Building
Naval Reserve Center, Louisville, Kentucky
Brief scope of work: Labor, material, and equipment to design, remove and replace the existing freight elevator with a hydraulic passenger elevator as well as build a new machine room in the boiler room complete and ready for use.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-07-C-2028 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$237,504.00 |
|
|
Period of Performance |
August 2008 – July 2009 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
Building 130 Interior Renovations
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Interior renovations of Building 130 including demolition, metal framing and siding, mechanical contracting, drywall installation and finishing, and personnel and overhead door installation.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0006 FRR080-147 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$221,118.00 |
|
|
Period of Performance |
October 2007 – September 2008 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |
Provide Quality Control Services to Building 41
Naval Support Activity, Crane, Indiana
Brief scope of work: Develop quality control plan for Building 41 and provide QC manager to Weddle Brothers Construction.
|
Contract Information |
||
|
Contract Owner |
Weddle Brothers Construction, Bloomington, IN |
|
|
Contract Number |
577 |
|
|
Contract Type |
Fixed Dollar |
|
|
Contract Value |
$215,725.00 |
|
|
Period of Performance |
April 2004 – September 2005 |
|
|
QC Manager |
Pete Davis |
(812) 201-1563 |
Install Fiber Optics Backbone, Automated Gates and Fencing
Naval Support Activity Center, Crane, Indiana
Brief scope of work: Provide Quality Control and Site Safety services for SAIC in addition to providing design quality control services and submittal reviews.
|
Contract Information |
||
|
Contract Owner |
SAIC |
|
|
Contract Number |
N40083-07-C-2016 Subcontract 447001401209 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$205,608.00 |
|
|
Period of Performance |
March 2007 – December 2007 |
|
|
Project Manager |
Gary Richardson |
(812) 384-3587 X-239 |

Building 351 Interior Renovations
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Interior renovations of Building 351 including demolition of interior and concrete access pads. Installation of metal fabrications, doors, carpet, VCT, acoustical ceiling tiles, installation of quarry tiles, and finish hollow metal doors & frames in Mechanical Room.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0-006 FRR080-152 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$193,768.00 |
|
|
Period of Performance |
October 2007 – October 2008 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |

Crane DNR Office and Additional Remodeling on Various Buildings
Naval Support Activity, Crane, Indiana
Brief scope of work: Installation of carpeting and modular furniture in the DNR office. Contract has consisted of ten amendments to date to include maintenance projects throughout the Crane Naval Station such as painting the bachelor quarters, carpeting and vinyl flooring in other buildings, drywall mold remediation, asbestos removal and window replacement.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-05-M-4461 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$193,717.92 |
|
|
Period of Performance |
July 2005 – May 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
Provide Quality Control Services to Joint Ordnance and Engineering Logistics Facility, Naval Support Activity, Crane, Indiana
Brief scope of work: Develop quality control plan and provide QC Manager to Weddle Brothers Construction for MACC design-build project, Construct Joint Ordnance and Engineering Logistics Facility.
|
Contract Information |
||
|
Contract Owner |
Weddle Brothers Construction, Bloomington, IN |
|
|
Contract Number |
102245 – Job 580 |
|
|
Contract Type |
Fixed Dollar |
|
|
Contract Value |
$173,828.00 |
|
|
Period of Performance |
June 2005 – September 2006 |
|
|
Contract Manager |
Jeff Mattix |
(812) 339-9500 |

Interior Finish Renovation, Building 220
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Renovation of Building 220 to include drywall, painting, flooring, acoustical ceiling, door installation and other interior work as described in the scope.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors, Inc., Paducah, KY |
|
|
Contract Number |
FRR080-50 |
|
|
Contract Type |
Fixed Dollar |
|
|
Contract Value |
$173,386.00 |
|
|
Period of Performance |
August 2006 – November 2006 |
|
|
Contract Manager |
Tom Medina |
(270) 442-8620 |
Construct Lab Room 114, Building 41
Naval Support Activity, Crane, Indiana
Brief scope of work: Provide all labor, equipment, tools, supplies, transportation, supervision, quality control and management necessary to construct laboratory in room 114, Building 41. Work includes constructing exterior wall complete with metal door, construct small room complete with metal door, painting all walls, install suspended ceiling, install ESD, epoxy floor, install safety rail around existing footer, install HVAC, sound doors and related electrical work.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest PWD Detachment, Crane IN |
|
|
Contract Number |
N40083-09-C-2232 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$165,931.00 |
|
|
Period of Performance |
April 2009 – November 2009 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |

Performance Oriented Construction Activity
Kansas City Corps of Engineers, Vet Kennel, Fort Leonard Wood, Missouri
Brief scope of work: Task Order #0001 - Remove existing structure, place footings, erect steel, install utilities, install interior mechanical and electrical systems, and finish.
|
Contract Information |
||
|
Contract Owner |
Kansas City District, Corp of Engineers |
|
|
Contract Number |
W912DQ-05-D-0031 DO #0001 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$154,523.00 |
|
|
Period of Performance |
February 2006 – April 2006 |
|
|
Contracting Officer |
Jesse Vance COE, Ft Leonard Wood |
(573) 596-0081 |



Rim Rock Trial Steps and Deck Replacement
Shawnee National Forest, Gallatin County, Illinois
Brief scope of work: Remove existing trail stairway and observation deck and replace with new.
|
Contract Information |
||
|
Contract Owner |
Monongahela National Forest 200 Sycamore Street Elkins, WV 26241 |
|
|
Contract Number |
43-3434-4-6051 |
|
|
Contract Type |
Best Value |
|
|
Contract Value |
$149,710.00 |
|
|
Period of Performance |
September 2004 – January 2005 |
|
|
Contracting Officer |
Mary E. Saint Louis |
(304) 636-1800 |
|
Contract Representative |
Cynthia Morris Harrisburg, IL |
(618) 253-1029 |


B-41 Humidify Sustainment Area
Naval Support Activity, Crane, Indiana
Brief Scope of Work: Labor, materials and equipment to install five wall mounted humidifiers, drain, steam distribution pipe, ductwork, steam distributors and controls in Building 41.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-08-C-2155 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$146,811.00 |
|
|
Period of Performance |
September 2008 – June 2009 |
|
|
Contracting Officer |
Debra Dills |
(812) 854-3234 |
Preventative Maintenance and Control Inspection
Marine Corps Reserve Center, Terre Haute, Indiana
Brief scope of work: Preventative maintenance and control inspections in accordance with contract at the Marine Corps Reserve Center. Base year contract plus one option years were awarded with the first inspections and maintenance beginning April 2006.
|
Contract Information |
||
|
Contract Owner |
Naval Facilities Engineering Command |
|
|
Contract Number |
N62467-06-R-2301 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$141,326.00 for total contractual period |
|
|
Period of Performance |
March 2006 – March 2008 |
|
|
Contract Specialist |
Troy Thompson |
(504) 678-6818 |
High Speed Deluge System & Twin Screw Extruder
Naval Support Activity, Crane, Indiana
Brief scope of work: Project consisted of installing Ultra High Speed Deluge Systems in Buildings 2963, 2995 and Building 3338.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-015-C-4488 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$139,252.99 |
|
|
Period of Performance |
September 2005 – December 2005 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
NAPEC Hasp Installation on Various Magazine Doors
Naval Support Activity, Crane Indiana
Brief scope of work: Provide labor, materials, supplies, equipment and supervision to install NAPEC hasps on various magazine doors and related work including lead paint abatement and safety/respirator training.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-06-M-4527 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$128,947.00 |
|
|
Period of Performance |
February 2006 – September 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
Construct Metal Enclosure with Roof for APE 1236 Furnace at Bldg 3343
Naval Support Activity, Crane, Indiana
Brief scope of work: This project is to construct a structural steel and metal sided enclosure for the APE furnace. Project includes new grade beam footer and expansion of mechanical room. This structure is unique in that the end product is required to be air tight.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-05-C-4465 |
|
|
Contract Type |
Negotiated Bid |
|
|
Contract Value |
$117,563.00 |
|
|
Period of Performance |
August 2005 – February 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
|
Contract Administrator |
Jeff Franz |
(812) 854-3318 |
|
Technical Representative |
Tim Sears |
(812) 854-3268 |
Zone 9 – Repair/Improve Access Roads
Naval Support Activity, Crane, Indiana
Brief scope of work: Develop quality control plan and provide QC Manager to Weddle Brothers Construction for this MACC project consisting of repairing and improving remote magazine storage building access roads and bridges.
|
Contract Information |
||
|
Contract Owner |
Weddle Brothers Construction Co., Bloomington, IN |
|
|
Contract Number |
N40083-06-D-4020-0003 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$111,200.00 |
|
|
Period of Performance |
December 2008 – September 2009 |
|
|
Contract Manager |
Jeff Mattix |
(812) 339-9500 |

Office Furniture in Building 56
Naval Support Activity, Crane, Indiana
Brief scope of work: This project consisted of procurement and installation of office furniture and partitions in Building 56.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-05-M-4489 |
|
|
Contract Type |
Negotiated Bid |
|
|
Contract Value |
$100,868.00 |
|
|
Period of Performance |
August 2005 – November 2005 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
Building 485 Repairs
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Renovations and repairs to Building 485 to include metal studs, drywall, insulation, painting and flooring as well as acoustical ceilings.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0-006 FRR080-171 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$100,191.00 |
|
|
Period of Performance |
April 2008 – August 2008 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |
Renovate Restrooms & Office, Building 101
Naval Support Activity, Crane, Indiana
Brief scope of work: Provide labor, equipment, material and supervision to renovate the men’s and women’s restrooms and office of Building 101 to include new fixtures, piping, drains, water heater, drinking fountain, potable water service piping, stud walls, insulation and drywall work, electrical wiring and lights, patching and painting and incidental work to provide complete and usable project.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-06-M-4557 |
|
|
Contract Type |
Fixed Dollar |
|
|
Contract Value |
$92,708.00 |
|
|
Period of Performance |
July 2006 – September 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |

Prep and Paint Building 101
Naval Support Activity, Crane, Indiana
Brief Scope of Work: All preparation of plaster, prime and paint Building 101 to include lead abatement, insulation, bathrooms, conduit, base strips and installing new door.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-06-M-4548 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$85,155.00 |
|
|
Period of Performance |
March 2006 – April 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |



Replace Windows at USCG Station Kenosha
Kenosha, Wisconsin
Brief scope of work: Remove and replace 81 windows at Coast Guard Station Kenosha.
|
Contract Information |
||
|
Contract Owner |
US Coast Guard Civil Engineering Unit Cleveland, OH |
|
|
Contract Number |
DTCG83-04-Q-3WF002 |
|
|
Contract Type |
Sealed Bid |
|
|
Contract Value |
$90,220.00 |
|
|
Period of Performance |
March 2004 – July 2004 |
|
|
Contracting Officer |
Verona M. Wolfe |
(216) 902-6265 |
|
Contract Administrator |
Verona M. Wolfe |
(216) 902-6265 |
|
Technical Representative |
Bill Henkelman |
(216) 902-6262 |
Building 103 Lab/Mezzanine Renovation
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Interior renovations of Building 103 to include mold remediation, drywall installation, carpeting, painting and door frame and hardware installation.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0-006 FRR080-159 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$83,982.00 |
|
|
Period of Performance |
July 2008 – September 2008 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |
Building 206 Tank Painting
NASA Michoud Assembly Facility, New Orleans, Louisiana
Brief scope of work: Prep and paint concrete tank including 6400 SF of roof surface area and 6400 SF of wall surface area. Work includes hydroblasting existing exterior walls and top to remove contaminates and loose, applying one coat of primer and two coats acrylic per plans and specifications. Work also included removing and reinstalling the 4000 psi concrete grout ring at the base of the tank.
|
Contract Information |
||
|
Contract Owner |
Vanguard Contractors |
|
|
Contract Number |
DACA87-03-D-0006 FRR080-143 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$76,339.00 |
|
|
Period of Performance |
August 2007 – October 2007 |
|
|
Contract Specialist |
Tom Medina |
(270) 442-8620 |

Renovation
of Comptroller Spaces, Building 64
Naval Support Activity, Crane,
Indiana
Brief scope of work: Renovation of Building 64 comptroller space to include drywall, painting, electrical work, carpeting, and installation of four doors and new furniture and cubicle installation.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-05-M-4578 |
|
|
Contract Type |
Firm-fixed price |
|
|
Contract Value |
$63,670.82 |
|
|
Period of Performance |
June 2006 – August 2006 |
|
|
Contracting Officer |
Tim Curry |
(812) 854-3537 |
Installation of Wood Frame Canopies in Residential Area
Naval Support Activity, Crane, Indiana
Brief scope of work: This project consists of replace deteriorated metal awnings on residences and replacing them with gable end canopies. 20 buildings are in this contract.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-05-M-4453 |
|
|
Contract Type |
Best Value |
|
|
Contract Value |
$54,444.44 |
|
|
Period of Performance |
September 2005 – November 2005 |
|
|
Contracting Officer |
Andrew Oddo |
(812) 854-4448 |
|
Technical Representative |
Tim Sears |
(812) 854-3268 |
Install Paint Booth, Building 155
Naval Support Activity, Crane, Indiana
Brief scope of work: Remove existing paint booth, fill in pit with materials as specified and install new paint booth, duct work, exhaust fan, conduit and wiring.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-06-M-4528 |
|
|
Contract Type |
Fixed Dollar |
|
|
Contract Value |
$48,636.00 |
|
|
Period of Performance |
July 2006 – September 2006 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
Intrusion Detection System
Naval Support Activity, Crane, Indiana
Brief scope of work: This project consists of replacing intrusion detection system in three (3) separate areas in Building 3330S and incidental related work.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-05-M-4490 |
|
|
Contract Type |
Firm Fixed |
|
|
Contract Value |
$35,485.00 |
|
|
Period of Performance |
September 2005 |
|
|
Contracting Officer |
Carrie Grimard |
(812) 854-6641 |
Tent City Communications
Naval Support Activity Center, Crane, Indiana
Brief scope of work: Labor, materials and supplies for installation of new data communications capability and all ancillary materials .and equipment required to support eight tent pads in the Tent City area of the compound.
|
Contract Information |
||
|
Contract Owner |
NAVFAC PWD Crane |
|
|
Contract Number |
N40083-08-M-2137 |
|
|
Contract Type |
Firm Fixed Price |
|
|
Contract Value |
$33,698.00 |
|
|
Period of Performance |
May 2008 – July 2008 |
|
|
Contract Specialist |
Debra Dills |
(812) 854-3234 |
Emergency Generator Repair
Wastewater Treatment Building 3049, Crane, Indiana
January 2008 – April 2008
Brief scope of work: Labor, materials, and supplies to repair the generator at the Waste Water Treatment Plant located at Naval Support Activity Center.
|
Contract Information |
||
|
Contract Owner |
NAVFAC Midwest Detachment, Crane, IN |
|
|
Contract Number |
N40083-08-M-2111 |
|
|
Contract Type |
Negotiated |
|
|
Contract Value |
$31,854.00 |
|
|
Period of Performance |
January 2008 – April 2008 |
|
|
Contracting Officer |
Carrie Grimard |